RIT process diagram text
Preliminary | Stage 1 | Stage 2 | Stage 3 | Determination | |
---|---|---|---|---|---|
Transmission | Preparation | Project Specification Consultation Report | Project Assessment Draft Report | Project Assessment Conclusion Report | AER Decision |
Distribution | Preparation and Notice | Non-Network Options Report | Draft Project Assessment Report | Final Project Assessment Report | |
Consultation Period | ~4 weeks | Minimum 12 weeks | Minimum 6 weeks | Open for dispute <30 days | NER requirement <120 business days |