This page is for you if you are an Installer, Solar Retailer or Registered Electrical Contractor (REC) and you are designing a system that is over 30kW and up to 1.5 MW. Installations of this size require a detailed technical assessment.
These are typically commercial or industrial systems that may require changes to the network to accommodate them. All of these systems will require Central Protection (refer to SOP 11-16).
The total administration fee for these projects is $2,200.25 (excl. GST) for systems up to 200kW and $7,600.25 (excl. GST) for systems greater than 200kW and up to 1.5MW. There may be additional fees if grid augmentation is required (such as us having to install extra poles and wires).
With large installations like this you will be responsible for undertaking specialised commissioning tests (SOP 33-07 & SOP 33-08) to demonstrate compliance with our requirements.
You will need pre-approval from us before you can start the installation.
Step 1. Submit your pre-approval application via email.
Step 2. We will then send you an invoice.
Step 3. Once the invoice is paid our technical assessors will evaluate your application for pre-approval.
Your proposed installation must comply with the requirements in the following documents:
Pre-approval application fees:
$200.25 (excl. GST)
Up to 20 business days - for us to raise the invoice.
Our technical assessors will evaluate your application. During this time they are doing the following:
To proceed with your application, you must send us:
$2,000 (excl. GST) for systems up to 200kW
$7,400 (excl. GST) for systems greater than 200kW and up to 1.5MW
65 business days - For initial pre-approval.
Upon receipt of your completed technical schedule, the 'For Construction' single line diagram and payment of the project fee, a final assessment will be completed by our technical assessors. If everything meets our requirements, you will receive an approval letter from us, this will include your site specific Connection Agreement.
During this time our technical assessors are doing the following:
If we need to strengthen the network to approve of the system (such as a bigger transformer or extra poles and wires), we will let you know the costs for this.
10 business days - Approximate time we need to accept your application for approval.
You may install the system after you have been given final approval by one of our technical assessors.
In order to undertake the commissioning tests, we will allow the temporary connection of the system. To do this you must submit a commission test program. Temporary connection cannot occur until the commission test program has been approved by us.
The final connection of the system is subject to all of the following:
There are no costs for this part of the process.
Before we can allow your customer to legally generate their own energy, you'll need to send the paperwork to us and your customer's retailer for final approval.
Send the following documents to your customers retailer, so that we can upgrade the meter:
There are no costs for this part of the process.
90 days - For you to install and submit the final paperwork before your pre-approval expires.
We will confirm that all the paperwork matches up to the Connection Agreement and store this information. Your customer's Metering Provider (this may or may not be us) will receive the Electronic Works Request (EWR) from your customers’ retailer. Their meter will then be reconfigured to record feed-in and their tariff will potentially change.
Your customer may now switch on the system and begin generating their own energy.
Your customer's energy retailer must request these metering changes from us (or their Metering Provider) before we can proceed.
There can only be one meter at each location. If there are more we will need to consolidate them - this requires a technician to visit the premises (truck visit).
If the premises does not have a smart meter, a manual reconfiguration will need to take place with a truck visit.
If we are the Metering provider: Your customer will be billed via their retailer:
$28.65 - Electronic Meter reconfiguration$335.00 - Truck visit (if applicable)
If we are the Metering provider: 10 business days - For us to approve the final installation and reconfigure the meter, after we receive it from the retailer.