If you are considering a 1500 kW to 5000 kW energy generation system this page is for you.
AusNet Services treats all applications between 1500 kW and 5000 kW under the Negotiated Connection framework as nominated in National Electricity Rules (NER) Chapter 5A. For description of the different connection services and the connection applicants rights under these process please see AusNet Services connection policy.
Below you will find information about the process, timeline and costs involved in connecting to the grid.
For connections greater than 5000 kW please see AusNet Services Website.
For connections to the Victorian Transmission Network, the Australian Energy Market Operator (AEMO) manages the connection process and is your main point of contact. For more details, please visit their website.
If you are considering a medium scale energy generation system this page is for you. Systems in this range are usually commercial or industrial systems connecting into the AusNet Services Medium Voltage (11KV/ 22KV) network and are between 1.5MW and 5MW in generating capacity.
Below you will find information about the process, timeline and costs involved in connecting to the grid.
- Read our Protection Requirements in SOP 11-16 for the Connection of Embedded Generators between 1.5MW to 5MW for information regarding technical standards
- Complete an Connection Application Form and send it to Energy Connections inbox energyconnectionsSG@ausnetservices.com.au
AusNet Services treats all applications between 1.5MW and 5MW under the Negotiated Connection framework as nominated in National Electricity Rules (NER) Chapter 5A. For description of the different connection services and the connection applicants rights under these process please see AusNet Services connection policy.
For connections greater than 5MW connecting into the 22KV/66KV network please see process on the AusNet Services Website.
For connections to the Victorian Transmission Network (220KV and above), the Australian Energy Market Operator (AEMO) manages the connection process and is your main point of contact. For more details, please visit their website.
If you are considering a medium scale energy generation system this page is for you. Systems in this range are usually commercial or industrial systems connecting into the AusNet Services Medium Voltage (11KV/ 22KV) network and are between 1.5MW and 5MW in generating capacity.
Below you will find information about the process, timeline and costs involved in connecting to the grid.
- Read our Protection Requirements in SOP 11-16 for the Connection of Embedded Generators between 1.5MW to 5MW for information regarding technical standards
- Complete an Connection Application Form and send it to Energy Connections inbox energyconnectionsSG@ausnetservices.com.au
AusNet Services treats all applications between 1.5MW and 5MW under the Negotiated Connection framework as nominated in National Electricity Rules (NER) Chapter 5A. For description of the different connection services and the connection applicants rights under these process please see AusNet Services connection policy.
For connections greater than 5MW connecting into the 22KV/66KV network please see process on the AusNet Services Website.
For connections to the Victorian Transmission Network (220KV and above), the Australian Energy Market Operator (AEMO) manages the connection process and is your main point of contact. For more details, please visit their website.
If you are considering a medium scale energy generation system this page is for you. Systems in this range are usually commercial or industrial systems connecting into the AusNet Services Medium Voltage (11KV/ 22KV) network and are between 1.5MW and 5MW in generating capacity.
Below you will find information about the process, timeline and costs involved in connecting to the grid.
- Read our Protection Requirements in SOP 11-16 for the Connection of Embedded Generators between 1.5MW to 5MW for information regarding technical standards
- Complete an Connection Application Form and send it to Energy Connections inbox energyconnectionsSG@ausnetservices.com.au
AusNet Services treats all applications between 1.5MW and 5MW under the Negotiated Connection framework as nominated in National Electricity Rules (NER) Chapter 5A. For description of the different connection services and the connection applicants rights under these process please see AusNet Services connection policy.
For connections greater than 5MW connecting into the 22KV/66KV network please see process on the AusNet Services Website.
For connections to the Victorian Transmission Network (220KV and above), the Australian Energy Market Operator (AEMO) manages the connection process and is your main point of contact. For more details, please visit their website.