The Regulatory Investment Test (RIT) is a cost benefit analysis overseen by the Australian Energy Regulator (AER). The purpose of a RIT is to identify the preferred network or non-network option to deliver the greatest economic benefit to market. The process also ensures investment decisions are in the long term interests of customers.
It assesses the economic and technical impact of major network investments in the national energy market above $6 million.
There are three broad stages we follow if a RIT is required for investment*.
Regulatory investment test for transmission |
||||
Identified Need |
Location |
Report |
Consultation Closes |
Status |
Maintain Supply Reliability |
Shepparton Terminal Station |
Project Assessment Conclusions Report Project Assessment Draft Report Project Specification Consultation Report |
4 Nov 2021 23 Jul 2021 18 Mar 2021 |
Closed Closed Closed |
Maintain Supply Reliability |
Sydenham Terminal Station |
Project Assessment Draft Report Project Specification Consultation Report Project Assessment Conclusions Report |
4 Oct 2021 15 Mar 2021 22 Nov 2021 |
Closed |
Corrective Action Reliability |
Horsham Terminal Station |
15 Jun 2021 |
Closed |
|
Maintain Supply Reliability | Moorabool Terminal Station | Project Specification Consultation Report | 23 June 2022 | Closed |
Maintain Supply Reliability |
Cranbourne Terminal Station |
Project Specification Consultation Report |
25 Sep 2020 |
Closed |
Corrective Action Reliability |
Murray Switching Station (MSS) to Dederang Terminal Station |
Project Specification Consultation Report |
22 July 2022 | Open |
Maintain Supply Reliability | Transmission Lines multiple circuits | Project Specification Consultation Report |
22 July 2022 |
Open |
Maintain Supply Reliability |
MLTS, HGTS, MOPS, TRTS, HYTS, APD, TGTS |
Project Specification Consultation Report | 18 August 2022 | Open |
Maintain Safety & Supply Reliability | Transmission lines multiple circuits | Project Specification Consultation Report | 13 September 2022 | Open |
Regulatory investment test for distribution |
||||
Identified Need | Location |
Report |
Consultation Closes | Status |
Maintain Supply Reliability | AusNet Distribution Network |
15 June 2022 N/A |
Closed Closed |
|
Reliability Corrective Action |
REFCL Tranche 1 & 2 |
31 May 2022 N/A |
Open Closed |
|
Service Constraints |
Maffra |
Final Project Assessment Report |
N/A 15 April 2022 N/A |
Closed Closed Closed |
Service Constraints | Bayswater |
31 May 2022 N/A |
Open Closed |
|
Service Constraints |
Clyde North |
Final Project Assessment Report |
N/A 22 April 2022 27 August 2021 |
Closed Closed Closed |
Service Constraints |
Traralgon |
20 August 2021 |
Closed |
|
Service Constraints | Warragul |
N/A 05 April 2022 |
Closed Closed |
|
Service Constraints |
Thomastown |
21 July 2021 |
Closed |
|
Service Constraints |
Benalla |
Non-Network Options Report |
21 July 2021 | Closed |
To get involved in RIT projects, please contact AusNet Services via rittconsultations@ausnetservices.com.au
Further information is also available in the Energy Networks Australia RIT-T handbook.
Under transitional provisions in the National Electricity Rules, the following in-flight projects are exempt from the Regulatory Investment Test.
Project name |
Location |
Scope of work summary |
Completion |
MD1000 RTU at Zone Substations | FTR, FGY, BWN, BGE, ELM, RWN, LDL, CLN, EPG, BRA, BN and BWA | Install and commission the RTU and local HMI. Connect RTU to all existing IEDs at these ZSS via their communication protocols e.g. DNP3, Modbus, IEC103 etc. Separate common alarms. Decommission existing RTU | 2023 |
Power Station Closure Works | HWPS | Mandatory compliance works, including various civil and electrical works related with closure of power station | 2023 |
Switchyard Redevelopment 220kV at Terminal Station | HWPS | Replace the remaining 220kV Bulk Oil Circuit Breakers and install remote operated isolators | 2022 |
Power Station Rebuild | YPS | Replace 66/11kV transformer, circuit breakers and other primary equipment | 2022 |
Redevelopment at Terminal Station | WMTS | Replace 220/66kV transformers, 220kV switch bays, 66kV switch bays and all protection and control systems. Retire two 220/22kV transformers and the 22 kV supply from WMTS | 2022 |
Circuit Breakers 500kV at Terminal Station | HYTS | Replace deteriorated 500kV switchgear | 2022 |
Static Var Compensator Control and Relays | ROTS | Install thyristors, controllers and cooling system on second SVC, and protection relay panels for both SVCs. Decommission old equipment. Replace reactors, capacitor cans, instrument transformers and faulty bus support insulators for both SVCs. Replace connections, and if found to be an issue, sections of bus-work |
2022 |
CCTV Upgrades at Terminal Stations | DDTS, ROTS, KTS, SMTS, HWTS, LYPS, JLTS | Upgrade CCTV surveillance |
2022 |
Primary and Secondary assets at Terminal Stations | TBTS, RCTS, TTS, MWTS, EPSY, LY | Replace 66kV CB CT and Isolators at all locations, 220kV CT CVTs at TBTS, EPSY, and 11kV and 22kV fuse isolators at RCTS and TBTS |
2022 |
Circuit Breakers 500kV at Terminal Stations | LYPS, HWTS | Replace 500kV circuit breakers |
2021 |
Circuit breakers 220/66kV at Terminal Station | FBTS | Replace B4 220/66kV transformer. Replace 220kV and 66kV circuit breakers |
2021 |
REFCL Tranche 2 | RWN, ELM, FGY, WOTS, MOE, BGE, LDL, BDL | Install REFCL equipment at each zone substation |
2021 |
North West Comms Network | BATS, HOTS, RCTS, KGTS, BETS |
Install OPGW from Murra Warra Terminal Station through Red Cliffs to KGTS. Install new microwave radio from KGTS to BETS. Install Optical Telecommunications Networking equipment at each sites and WDM where required for hop distance. |
2021 |
Identified Need |
Location |
Report |
Consultation Closes |
Status |
Reliability Corrective Action |
REFCL Tranche 3 |
Final Project Assessment Report Draft Project Assessment Report Notice of Determination |
2 June 2021 27 April 2021 N/A |
Closed Closed Closed |