RIT process diagram text

  Preliminary Stage 1 Stage 2 Stage 3 Determination
Transmission Preparation Project Specification Consultation Report Project Assessment Draft Report Project Assessment Conclusion Report AER Decision
Distribution Preparation and Notice Non-Network Options Report Draft Project Assessment Report Final Project Assessment Report
Consultation Period ~4 weeks Minimum 12 weeks Minimum 6 weeks Open for dispute <30 days NER requirement <120 business days 
*Depending on the complexity and requirements of each project, not all stages will be required to satisfy the RIT process.